Site Bulletin No. 11 – Eco Report

Please find below the Environmental Credentials report for the new Teaching Block.
Read More

Site Bulletin No.10 – 12th July 2019

We are all very excited now that the Teaching Block is reaching the final stages of construction and we look forward to moving in at the end of July. Over the last couple of months, progress has been very rapid. In April, the building had no windows and the roof had not yet been fully completed but the contractors have made every effort to make sure we are now able...
Read More

Site Bulletin No.9 – 25th April 2019

A lot of progress has been made during the Easter holidays. The building is now connected to all services and IT, fire and CCTV links have been made to existing buildings. Curtain walling is currently being installed.
Read More

Site Bulletin No.8 – 28th March 2019

Internal mechanical and electrical works are now at an advanced stage and the central staircase has now been installed. The classrooms are now very recognisable!
Read More

Site Bulletin No.7 – 27th February 2019

Now that the building envelope is complete, we will be saying goodbye to the tower crane in early March. Internal works are ahead of schedule but the snow and high winds over the winter have brought some delays to external works. We are hoping this current good weather continues.
Read More