Site Bulletin No.12 – 23rd September 2019

We are very pleased that the new teaching block is now in full use. The landscaping works are well under way and should be finished by Christmas weather permitting. The demolition is all complete. Snagging will continue over the next few months to iron out the final details but overall we are delighted with our …

Continue reading

Site Bulletin No. 11 – Eco Report

Please find below the Environmental Credentials report for the new Teaching Block.

Site Bulletin No.10 – 12th July 2019

We are all very excited now that the Teaching Block is reaching the final stages of construction and we look forward to moving in at the end of July.

Over the last couple of months, progress has been very rapid. In April, the building had no windows and the roof had not yet been fully …

Continue reading

Site Bulletin No.9 – 25th April 2019

A lot of progress has been made during the Easter holidays. The building is now connected to all services and IT, fire and CCTV links have been made to existing buildings. Curtain walling is currently being installed.

Site Bulletin No.8 – 28th March 2019

Internal mechanical and electrical works are now at an advanced stage and the central staircase has now been installed. The classrooms are now very recognisable!

Site Bulletin No.7 – 27th February 2019

Now that the building envelope is complete, we will be saying goodbye to the tower crane in early March. Internal works are ahead of schedule but the snow and high winds over the winter have brought some delays to external works. We are hoping this current good weather continues.

Site Bulletin No.6 – 4th February 2019

Despite problems with the winter weather causing a few delays, we are making great progress on the teaching block. A ‘Topping Out’ ceremony was held to mark the completion of the roof- a significant milestone. Our internal fixtures and fittings wish list is complete and we will be ordering as soon as all our funding …

Continue reading

Site Bulletin No.5 – 28th November 2018

We are now at full height with the roof slab in place and stairs installed. Brickwork to start in January. We were very pleased that one of our students has been able to spend a day’s work experience on the site with Evers. All going really well so far!

Site Bulletin No.4 – 31st October 2018

The building is progressing very rapidly and we are now up to roof level. These photos were taken before the second floor concrete pour but give an indication of the work involved.

Site Bulletin No.3 – 21st September 2018

Here is the latest bulletin from our builders. It is progressing very quickly with the foundations now completed. We will all start to notice big changes as it ‘grows’ out of the ground.